Seadrill orders four more newbuild drillships

JULY 15, 2013 — John Fredriksen's Seadrill Limited has entered into turnkey contracts to build four new ultra-deepwater drillships at Korean shipyards. Two will be built at DSME and two at Samsung. The project value price is estimated to be below US$600 million per unit (including project management, drilling and handling tools, spares, capitalized interest and operations preparations). Delivery of the four units is scheduled for the second half 2015 and Seadrill has received fixed priced options for delivery of two further units in the first half 2016.

"We have been able to use the current weakness in the shipbuilding industry to order drilling units at very attractive price levels," says Mr. Fredriksen. "At the same time we are securing future growth by continuing to build a homogenous fleet with all the operational benefits which come from fleet standardization."

Seadrill says it expects that the four newbuilds can be fully financed through a combination of available cash and structured debt facilities, and that no additional equity or reduction in dividend capacity will be needed to support and complete the project.

The drillships will have a hook load capability of 1,250 tons and a water depth capacity of up to 12,000 feet targeting operations in areas such as the Gulf of Mexico, Brazil and West and East Africa. Also, these units will be outfitted with seven ram configuration of the blowout preventer (BOP) stack and with storing and handling capacity for a second BOP. The units include design and equipment features, which makes them particularly attractive for development drilling. For two of the drillships, Seadrill has options to include equipment that prepares the units 20K BOP systems.

Seadrill's construction program now totals 22 units, including 9 drillships, 2 harsh environment semi-submersibles, and 11 high specification jack-ups. In addition, it has fixed priced options for two ultra-deepwater units.

The offshore drilling market has absorbed approximately 261 new units since 2005 and the utilization of the ultra deepwater fleet has been 100 percent since Seadrill was established in 2005. In the same period offshore production has been estimated to be marginally down. Seadrill says that this illustrates in very simple terms the increased complexity of the development of new oil and gas reserves.

Seadrill has spent significant time and effort analyzing the future demand of the ultra deepwater drilling market. Ultra deepwater production is estimated to increase from around 1 million barrels per day today to 5 million barrels per day over the next 6 years. In order to reach this target significant new development drilling capacity will have to be added. At the same time, the industry faces a situation where approximately 49 percent of the current floater fleet is older than 20 years. Seadrill says it has already seen a strong trend whereby fourth and fifth generation vessels are incapable of meeting oil companies' new requirement for safety margin and deck load capacity and are being replaced with newer units.

The Board of Seadrill is of the opinion that the current order book for 2014 - 2016 of approximately 39 units will be fully absorbed, and utilization will continue at very high levels with solid dayrates for the modern equipment.

Seadrill currently has an order backlog of approximately $19 billion. Based on current discussions, it is confident that in the coming months it will add to this as itd open 2014 capacity is likely to be fixed at attractive day rate levels.

Seadrill believes that the economic and administrative benefits of organic growth are far superior to large corporate acquisitions. The decision to move ahead with the four latest newbuilds has been taken after a careful consideration of Seadrill's financing capacity, and is partly a reflection of the increased financial flexibility created by the sale of the tender rig fleet to Sapura Kencana. The board has during the last year also seen significant improvement in Seadrill's borrowing capacity. This trend is supported by strong improvement in operating results as well as increased credibility in the ECA market, the bond market as well as lower margins from commercial banks.

Seadrill says industry ordering of deep water drilling units for 2015 delivery has been lower than expected with only seven un-contracted newbuilds available prior to this order.

"It is unlikely that our competitors can add any significant additional capacity before the second part of 2016," says Seadrill. "We are comfortable that based on our current asset composition, quality of operation and capital structure we will be able to keep our target of delivering better returns for our shareholders than any of our industry peers. The Board continues to be excited about the strong demand for drilling and the overall tightness in the supply demand situation."

15 July 2013
[ad-side]
[ad-side]
[ad-side]
[ad-side]
[ad-side]
[ad-side]
[ad-side]
[ad-side]
[ad-side]
[ad-side]